OPTIMALISASI PENJADWALAN PEMELIHARAAN PESAWAT TERBANG: PERBANDINGAN MILP DAN SGS UNTUK PENGELOLAAN WAKTU, SUMBER DAYA, DAN RISIKO JADWAL
Abstract
This quantitative computational study evaluates the scheduling of two anonymized aircraft maintenance projects comprising 626 activities, 709 precedence relationships and 13 shared resource categories. A mixed-integer linear programming (MILP) schedule is assessed against a serial schedule generation scheme (SGS) under identical PERT expected durations and resource constraints, using Python in Anaconda. Both schedules attain an overall makespan of 57,078 minutes, yet MILP shortens Project A completion by 1,796 minutes (10.49%) against SGS. Workload and horizon-wide average resource utilization are equal, whereas SGS exhibits lower temporal load variation in five categories. Existing 10,000-run resource-aware Beta-PERT Monte Carlo simulations indicate a 5.2% probability of meeting the deterministic completion target, with a P90 duration of 58,872.01 minutes. The findings establish a project-level schedule trade-off but do not demonstrate combined makespan savings or verified gains in individual labor productivity. Inferences remain conditional on calibrated activity-level uncertainty parameters and modeled resource requirements.
References
[2] G. Chen, W. He, Y. Tian, and K. Ma, “Resource-constrained project scheduling with multiple states: Bi-objective optimization model and case study of aircraft maintenance,” Comput Ind Eng, vol. 191, 2024, doi: 10.1016/j.cie.2024.110169.
[4] J. Adimonyemma and Y. Sun, “Optimization model for large-scale long-term aircraft maintenance scheduling and station assignment,” Transp. Res. Part E Logist. Transp. Rev., vol. 202, 2025, doi: 10.1016/j.tre.2025.104302.
F. Agostinho, M. Martinho, T. Alves, and A. R. Andrade, “Planning maintenance tasks in airline operating companies: A mathematical programming model applied to a case study,” Proc. Inst. Mech. Eng. Part O J. Risk Reliab., vol. 239, no. 6, pp. 1609–1629, 2025, doi: 10.1177/1748006X251317248.
[8] C. Li, Y. Zhang, X. Su, and X. Wang, “An Improved Optimization Algorithm for Aeronautical Maintenance and Repair Task Scheduling Problem,” Mathematics, vol. 10, no. 20, 2022, doi: 10.3390/math10203777.
[9] K. Pimapunsri, D. Weeranant, and A. Riel, “Genetic Algorithms For The Resource-Constrained Project Scheduling Problem In Aircraft Heavy Maintenance,” Suranaree J. Sci. Technol., vol. 28, no. 6, 2021, [Online]. Available: https://www.scopus.com/inward/record.uri?eid=2-s2.0-85130588829&partnerID=40&md5=ae5da44f7f4a38c8a48062079343dc42
[5] D. S. Altner et al., “Military aircraft flight and maintenance scheduling with many additional considerations,” J. Def. Model. Simul., 2025, doi: 10.1177/15485129251383566.
[6] G. Cha, J. Park, and I. Moon, “Military aircraft flight and maintenance planning model considering heterogeneous maintenance tasks,” Reliab Eng Syst Saf, vol. 239, 2023, doi: 10.1016/j.ress.2023.109497.
J. Zeng et al., “A Hybrid Reverse Learning Particle Swarm Optimization Method for Aircraft Maintenance Scheduling Based on the Resource-Constrained Project Scheduling Problem Model,” Mach., vol. 14, no. 6, 2026, doi: 10.3390/machines14060622.
[11] L. Qi, C. Lv, T. Zhang, and Y. Wang, “Dynamic multi-objective aviation maintenance scheduling: an algorithmic framework,” Sci. Rep., vol. 16, no. 1, 2026, doi: 10.1038/s41598-026-40304-0.
[12] Z. Guo, X. Wen, and X. Huang, “Aircraft maintenance scheduling optimization: state-of-the-art and emerging trends,” Transp. Res. Part E Logist. Transp. Rev., vol. 209, 2026, doi: 10.1016/j.tre.2026.104767.
[13] X. Hu, R. Na, and H. Li, “Intelligent Scheduling Optimization for Multi-aircraft Collaborative Maintenance,” Jiaotong Yunshu Xitong Gongcheng Yu Xinxi J. Transp. Syst. Eng. Inf. Technol., vol. 26, no. 2, pp. 148–158, 2026, doi: 10.16097/j.cnki.1009-6744.2026.02.014.
S. Mozhdehi, V. Baradaran, and A. H. Hosseinian, “Multi-skilled resource-constrained multi-project scheduling problem with dexterity improvement of workforce,” Autom Constr, vol. 162, 2024, doi: 10.1016/j.autcon.2024.105360.
[16] E. Goudarzi, H. Esmaeeli, K. Parsa, and S. Asadzadeh, “Proposing new clustering-based algorithms for the multi-skilled resource-constrained multi-project scheduling problem with resource leveling adjustments,” Kybernetes, vol. 54, no. 2, pp. 1049–1081, 2025, doi: 10.1108/K-06-2023-1044.
[17] M. Aghileh, A. Tereso, F. Alvelos, and M. O. Monteiro Lopes, “Multi-project scheduling under uncertainty and resource flexibility: a systematic literature review,” Prod. Manuf. Res., vol. 12, no. 1, 2024, doi: 10.1080/21693277.2024.2319574.
[18] S. Soltan and M. Ashrafi, “A new optimization model for multi-project scheduling considering dynamic resource allocation,” Soft Comput., vol. 29, no. 15–16, pp. 5143–5158, 2025, doi: 10.1007/s00500-025-10891-7.
[19] S. Khajesaeedi, S. J. Sadjadi, F. Barzinpour, and R. T. Moghaddam, “Resource-constrained project scheduling problem: Review of recent developments,” J. Proj. Manag., vol. 10, no. 1, pp. 1–26, 2025, doi: 10.5267/j.jpm.2024.12.002
M. Farahmand-Mehr and S. M. Mousavi, “Resource-constrained multi-project scheduling problems considering time-dependent reliability of resources: a new immune genetic local search algorithm,” Kybernetes, vol. 55, no. 6, pp. 2571–2606, 2026, doi: 10.1108/K-04-2024-0895.
[21] H. Ding, C. Zhuang, and J. Liu, “Extensions of the resource-constrained project scheduling problem,” Autom Constr, vol. 153, 2023, doi: 10.1016/j.autcon.2023.104958.
[22] K. Qiu, L. Chen, and S. Dauzère-Pérès, “Robust optimization approach for the resource-constrained project scheduling problem with uncertain activity release times,” Comp. Oper. Res., vol. 184, 2025, doi: 10.1016/j.cor.2025.107215.
[23] R. K. Chakrabortty, H. F. Rahman, K. M. A. Haque, S. K. Paul, and M. J. Ryan, “An event-based reactive scheduling approach for the Resource Constrained Project Scheduling Problem with unreliable resources,” Comput Ind Eng, vol. 151, 2021, doi: 10.1016/j.cie.2020.106981.
[24] J. Peng, W. Gao, Y. Li, S. He, K. Wang, and M. Xu, “A heuristic solution for multi-mode resource-constrained project scheduling problem with transfer times: The multi-project case,” Expert Sys Appl, vol. 290, 2025, doi: 10.1016/j.eswa.2025.128122.
[25] D. A. Peña, A. F. Osorio, J. P. Orejuela, and J. C. Idarraga, “Multi-skilled workforce scheduling with training and welfare considerations,” Eng. Manag. Prod. Serv., vol. 15, no. 3, pp. 27–41, 2023, doi: 10.2478/emj-2023-0018.
[26] M. Fekri, M. Heydari, and M. Mahdavi Mazdeh, “Bi-objective optimization of flexible flow shop scheduling problem with multi-skilled human resources,” Eng Appl Artif Intell, vol. 133, 2024, doi: 10.1016/j.engappai.2024.108094.
R. M. S. Avief and S. Hidayat, “A Risk-Integrated CPM-PERT and Monte Carlo Simulation Approach for Aircraft Overhaul Scheduling: Empirical Evidence from Military Maintenance Systems,” J. Eur. Syst. Autom., vol. 59, no. 3, pp. 641–649, 2026, doi: 10.18280/jesa.590308.
[29] O. S. Okunade, M. N. Obuseh, and O. E. Charles-Owaba, “Preventive maintenance scheduling of fleet of aircraft using contiguous-cells transportation model: A case study,” Int. J. Ind. Syst. Eng., vol. 39, no. 2, pp. 247–269, 2021, doi: 10.1504/IJISE.2021.118287.
[30] A. E. E. Eltoukhy, F. T. S. Chan, S. H. Chung, and B. Niu, “A model with a solution algorithm for the operational aircraft maintenance routing problem,” Comput Ind Eng, vol. 120, pp. 346–359, 2018, doi: 10.1016/j.cie.2018.05.002.
[31] M. Zhang et al., “An approximate dynamic programming approach for solving aircraft fleet engine maintenance problem: Methodology and a case study,” Eur J Oper Res, vol. 321, no. 3, pp. 958–973, 2025, doi: 10.1016/j.ejor.2024.10.008.
A. Giacotto, H. C. Marques, and A. Martinetti, “Prescriptive maintenance: a comprehensive review of current research and future directions,” J. Qual. Maint. Eng., vol. 31, no. 1, pp. 129–173, 2025, doi: 10.1108/JQME-07-2023-0064.
I. Stanton, K. Munir, A. Ikram, and M. El-Bakry, “Predictive maintenance analytics and implementation for aircraft: Challenges and opportunities,” Syst. Eng., vol. 26, no. 2, pp. 216–237, 2023, doi: 10.1002/sys.21651.
A. Giacotto, H. C. Marques, and A. Martinetti, “Prescriptive maintenance: a comprehensive review of current research and future directions,” J. Qual. Maint. Eng., vol. 31, no. 1, pp. 129–173, 2025, doi: 10.1108/JQME-07-2023-0064.
[36] J. N. M. Filho, A. C. P. de Mesquita, F. T. M. Abrahão, and G. C. Rocha, “An innovative method to solve the maintenance task allocation and packing problem,” J. Qual. Maint. Eng., vol. 30, no. 1, pp. 284–305, 2024, doi: 10.1108/JQME-08-2023-0069.
[37] Y. An, X. Chen, Y. Li, J. Zhang, and J. Jiang, “Flexible job-shop scheduling and heterogeneous repairman assignment with maintenance time window and employee timetable constraints,” Expert Sys Appl, vol. 186, 2021, doi: 10.1016/j.eswa.2021.115693.
[38] P. Alvarez-Campana, F. Villafanez, F. Acebes, and D. Poza, “Simulation-Based Approach For Multiproject Scheduling Based On Composite Priority Rules,” Int. J. Simul. Model., vol. 23, no. 1, pp. 29–40, 2024, doi: 10.2507/IJSIMM23-1-667.