OPTIMALISASI PENJADWALAN PEMELIHARAAN PESAWAT TERBANG: PERBANDINGAN MILP DAN SGS UNTUK PENGELOLAAN WAKTU, SUMBER DAYA, DAN RISIKO JADWAL

  • Grace Citra Dewi Master’s Program in Innovation Management, Faculty of Economics and Business, Ma Chung University, Malang, Indonesia
  • Raden Mohammad Suaidy Avief Tentara Nasional Indonesia Angkatan Udara (TNI AU)
  • Irhamsyah Pemerintah Provinsi Kalimantan Timur
Keywords: aircraft maintenance; mixed-integer linear programming; resource-constrained project scheduling; Monte Carlo; resource leveling

Abstract

This quantitative computational study evaluates the scheduling of two anonymized aircraft maintenance projects comprising 626 activities, 709 precedence relationships and 13 shared resource categories. A mixed-integer linear programming (MILP) schedule is assessed against a serial schedule generation scheme (SGS) under identical PERT expected durations and resource constraints, using Python in Anaconda. Both schedules attain an overall makespan of 57,078 minutes, yet MILP shortens Project A completion by 1,796 minutes (10.49%) against SGS. Workload and horizon-wide average resource utilization are equal, whereas SGS exhibits lower temporal load variation in five categories. Existing 10,000-run resource-aware Beta-PERT Monte Carlo simulations indicate a 5.2% probability of meeting the deterministic completion target, with a P90 duration of 58,872.01 minutes. The findings establish a project-level schedule trade-off but do not demonstrate combined makespan savings or verified gains in individual labor productivity. Inferences remain conditional on calibrated activity-level uncertainty parameters and modeled resource requirements.

References

D. Dinis, A. Barbosa-Póvoa, and Â. P. Teixeira, “A supporting framework for maintenance capacity planning and scheduling: Development and application in the aircraft MRO industry,” Int J Prod Econ, vol. 218, pp. 1–15, 2019, doi: 10.1016/j.ijpe.2019.04.029.
[2] G. Chen, W. He, Y. Tian, and K. Ma, “Resource-constrained project scheduling with multiple states: Bi-objective optimization model and case study of aircraft maintenance,” Comput Ind Eng, vol. 191, 2024, doi: 10.1016/j.cie.2024.110169.
[4] J. Adimonyemma and Y. Sun, “Optimization model for large-scale long-term aircraft maintenance scheduling and station assignment,” Transp. Res. Part E Logist. Transp. Rev., vol. 202, 2025, doi: 10.1016/j.tre.2025.104302.
F. Agostinho, M. Martinho, T. Alves, and A. R. Andrade, “Planning maintenance tasks in airline operating companies: A mathematical programming model applied to a case study,” Proc. Inst. Mech. Eng. Part O J. Risk Reliab., vol. 239, no. 6, pp. 1609–1629, 2025, doi: 10.1177/1748006X251317248.
[8] C. Li, Y. Zhang, X. Su, and X. Wang, “An Improved Optimization Algorithm for Aeronautical Maintenance and Repair Task Scheduling Problem,” Mathematics, vol. 10, no. 20, 2022, doi: 10.3390/math10203777.
[9] K. Pimapunsri, D. Weeranant, and A. Riel, “Genetic Algorithms For The Resource-Constrained Project Scheduling Problem In Aircraft Heavy Maintenance,” Suranaree J. Sci. Technol., vol. 28, no. 6, 2021, [Online]. Available: https://www.scopus.com/inward/record.uri?eid=2-s2.0-85130588829&partnerID=40&md5=ae5da44f7f4a38c8a48062079343dc42

[5] D. S. Altner et al., “Military aircraft flight and maintenance scheduling with many additional considerations,” J. Def. Model. Simul., 2025, doi: 10.1177/15485129251383566.
[6] G. Cha, J. Park, and I. Moon, “Military aircraft flight and maintenance planning model considering heterogeneous maintenance tasks,” Reliab Eng Syst Saf, vol. 239, 2023, doi: 10.1016/j.ress.2023.109497.
J. Zeng et al., “A Hybrid Reverse Learning Particle Swarm Optimization Method for Aircraft Maintenance Scheduling Based on the Resource-Constrained Project Scheduling Problem Model,” Mach., vol. 14, no. 6, 2026, doi: 10.3390/machines14060622.
[11] L. Qi, C. Lv, T. Zhang, and Y. Wang, “Dynamic multi-objective aviation maintenance scheduling: an algorithmic framework,” Sci. Rep., vol. 16, no. 1, 2026, doi: 10.1038/s41598-026-40304-0.
[12] Z. Guo, X. Wen, and X. Huang, “Aircraft maintenance scheduling optimization: state-of-the-art and emerging trends,” Transp. Res. Part E Logist. Transp. Rev., vol. 209, 2026, doi: 10.1016/j.tre.2026.104767.
[13] X. Hu, R. Na, and H. Li, “Intelligent Scheduling Optimization for Multi-aircraft Collaborative Maintenance,” Jiaotong Yunshu Xitong Gongcheng Yu Xinxi J. Transp. Syst. Eng. Inf. Technol., vol. 26, no. 2, pp. 148–158, 2026, doi: 10.16097/j.cnki.1009-6744.2026.02.014.
S. Mozhdehi, V. Baradaran, and A. H. Hosseinian, “Multi-skilled resource-constrained multi-project scheduling problem with dexterity improvement of workforce,” Autom Constr, vol. 162, 2024, doi: 10.1016/j.autcon.2024.105360.
[16] E. Goudarzi, H. Esmaeeli, K. Parsa, and S. Asadzadeh, “Proposing new clustering-based algorithms for the multi-skilled resource-constrained multi-project scheduling problem with resource leveling adjustments,” Kybernetes, vol. 54, no. 2, pp. 1049–1081, 2025, doi: 10.1108/K-06-2023-1044.
[17] M. Aghileh, A. Tereso, F. Alvelos, and M. O. Monteiro Lopes, “Multi-project scheduling under uncertainty and resource flexibility: a systematic literature review,” Prod. Manuf. Res., vol. 12, no. 1, 2024, doi: 10.1080/21693277.2024.2319574.
[18] S. Soltan and M. Ashrafi, “A new optimization model for multi-project scheduling considering dynamic resource allocation,” Soft Comput., vol. 29, no. 15–16, pp. 5143–5158, 2025, doi: 10.1007/s00500-025-10891-7.
[19] S. Khajesaeedi, S. J. Sadjadi, F. Barzinpour, and R. T. Moghaddam, “Resource-constrained project scheduling problem: Review of recent developments,” J. Proj. Manag., vol. 10, no. 1, pp. 1–26, 2025, doi: 10.5267/j.jpm.2024.12.002
M. Farahmand-Mehr and S. M. Mousavi, “Resource-constrained multi-project scheduling problems considering time-dependent reliability of resources: a new immune genetic local search algorithm,” Kybernetes, vol. 55, no. 6, pp. 2571–2606, 2026, doi: 10.1108/K-04-2024-0895.
[21] H. Ding, C. Zhuang, and J. Liu, “Extensions of the resource-constrained project scheduling problem,” Autom Constr, vol. 153, 2023, doi: 10.1016/j.autcon.2023.104958.
[22] K. Qiu, L. Chen, and S. Dauzère-Pérès, “Robust optimization approach for the resource-constrained project scheduling problem with uncertain activity release times,” Comp. Oper. Res., vol. 184, 2025, doi: 10.1016/j.cor.2025.107215.
[23] R. K. Chakrabortty, H. F. Rahman, K. M. A. Haque, S. K. Paul, and M. J. Ryan, “An event-based reactive scheduling approach for the Resource Constrained Project Scheduling Problem with unreliable resources,” Comput Ind Eng, vol. 151, 2021, doi: 10.1016/j.cie.2020.106981.
[24] J. Peng, W. Gao, Y. Li, S. He, K. Wang, and M. Xu, “A heuristic solution for multi-mode resource-constrained project scheduling problem with transfer times: The multi-project case,” Expert Sys Appl, vol. 290, 2025, doi: 10.1016/j.eswa.2025.128122.
[25] D. A. Peña, A. F. Osorio, J. P. Orejuela, and J. C. Idarraga, “Multi-skilled workforce scheduling with training and welfare considerations,” Eng. Manag. Prod. Serv., vol. 15, no. 3, pp. 27–41, 2023, doi: 10.2478/emj-2023-0018.
[26] M. Fekri, M. Heydari, and M. Mahdavi Mazdeh, “Bi-objective optimization of flexible flow shop scheduling problem with multi-skilled human resources,” Eng Appl Artif Intell, vol. 133, 2024, doi: 10.1016/j.engappai.2024.108094.
R. M. S. Avief and S. Hidayat, “A Risk-Integrated CPM-PERT and Monte Carlo Simulation Approach for Aircraft Overhaul Scheduling: Empirical Evidence from Military Maintenance Systems,” J. Eur. Syst. Autom., vol. 59, no. 3, pp. 641–649, 2026, doi: 10.18280/jesa.590308.
[29] O. S. Okunade, M. N. Obuseh, and O. E. Charles-Owaba, “Preventive maintenance scheduling of fleet of aircraft using contiguous-cells transportation model: A case study,” Int. J. Ind. Syst. Eng., vol. 39, no. 2, pp. 247–269, 2021, doi: 10.1504/IJISE.2021.118287.
[30] A. E. E. Eltoukhy, F. T. S. Chan, S. H. Chung, and B. Niu, “A model with a solution algorithm for the operational aircraft maintenance routing problem,” Comput Ind Eng, vol. 120, pp. 346–359, 2018, doi: 10.1016/j.cie.2018.05.002.
[31] M. Zhang et al., “An approximate dynamic programming approach for solving aircraft fleet engine maintenance problem: Methodology and a case study,” Eur J Oper Res, vol. 321, no. 3, pp. 958–973, 2025, doi: 10.1016/j.ejor.2024.10.008.
A. Giacotto, H. C. Marques, and A. Martinetti, “Prescriptive maintenance: a comprehensive review of current research and future directions,” J. Qual. Maint. Eng., vol. 31, no. 1, pp. 129–173, 2025, doi: 10.1108/JQME-07-2023-0064.
I. Stanton, K. Munir, A. Ikram, and M. El-Bakry, “Predictive maintenance analytics and implementation for aircraft: Challenges and opportunities,” Syst. Eng., vol. 26, no. 2, pp. 216–237, 2023, doi: 10.1002/sys.21651.
A. Giacotto, H. C. Marques, and A. Martinetti, “Prescriptive maintenance: a comprehensive review of current research and future directions,” J. Qual. Maint. Eng., vol. 31, no. 1, pp. 129–173, 2025, doi: 10.1108/JQME-07-2023-0064.
[36] J. N. M. Filho, A. C. P. de Mesquita, F. T. M. Abrahão, and G. C. Rocha, “An innovative method to solve the maintenance task allocation and packing problem,” J. Qual. Maint. Eng., vol. 30, no. 1, pp. 284–305, 2024, doi: 10.1108/JQME-08-2023-0069.
[37] Y. An, X. Chen, Y. Li, J. Zhang, and J. Jiang, “Flexible job-shop scheduling and heterogeneous repairman assignment with maintenance time window and employee timetable constraints,” Expert Sys Appl, vol. 186, 2021, doi: 10.1016/j.eswa.2021.115693.
[38] P. Alvarez-Campana, F. Villafanez, F. Acebes, and D. Poza, “Simulation-Based Approach For Multiproject Scheduling Based On Composite Priority Rules,” Int. J. Simul. Model., vol. 23, no. 1, pp. 29–40, 2024, doi: 10.2507/IJSIMM23-1-667.
Published
2026-11-24
How to Cite
Citra Dewi, G., Avief, R. M. S., & Irhamsyah. (2026). OPTIMALISASI PENJADWALAN PEMELIHARAAN PESAWAT TERBANG: PERBANDINGAN MILP DAN SGS UNTUK PENGELOLAAN WAKTU, SUMBER DAYA, DAN RISIKO JADWAL. Arthavidya Jurnal Ilmiah Ekonomi, 28(2), 294 - 314. https://doi.org/10.37303/a.v28i2.705
Section
Articles